The blueprints for the new construction projects have been completed and construction is ready to begin. See below option for answer.

 While the organization was thinking about erecting a modular structure, they decided on a more traditional approach. The foundation will be poured and cured before the framing begins. This is an example of:

a. Discretionary dependency

b. Mandatory dependency

c. External dependency

d. Internal dependency

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/15
sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

Mandatory dependency,

Thanks for invite

Utilisateur supprimé
par Utilisateur supprimé

The correct answer is 

b. Mandatory dependency

Piotr Teteruk
par Piotr Teteruk , IT Project Manager Roche , Roche

I answer is only B. The foundation must set before you can start erecting the walls of the structure. 

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option B