originally planned. Based on the current project timeline, product testing will have to be cut short. You have reviewed several options with the customer; they have decided that crashing the schedule would be the best approach to bringing in the project earlier. As a result of customer’s decision, what is your biggest concern using this approach? a. Additional expense b. Availability of additional resources to perform testing in a shorter time frame c. Customer buy-in d. Developing an adequate reward system to address the overtime that will be needed to bring in this project one month early
Agree on experts answers. Thanks
B – The technique that uses modeling is the Monte Carlo analysis. Answer ‘C’ is a constrained optimization method. Answers ‘A’ and ‘D’ are red herrings
.................a. Additional expense