A finish to finish relationship is defined as which of the following?

 

a. Both activities have to finish at the same time

b. The predecessor has to finish before the successor can finish

c. Both activities are on the critical path

d. The predecessor has a defined lead while the successor has a defined lag

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/16
Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

No.B ..............   a Successor Activity cannot finish until a Predecessor Activity has finished

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

Ghada Eweda
par Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

Agree on expert answers. Thanks

Abdullah Altuwayjiri
par Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

a. Both activities have to finish at the same time

VINOD KUMAR
par VINOD KUMAR , Manager-Planning and PMO , Voltas Limited

Both activites have to finish at same time irrespective of their start dates.

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

I agree with A option...........

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

A is the correct answer ...........

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B - This is the definition of a finish to finish relationship: I must complete activity ‘a’ before I complete

Activity ‘b’