Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The customer has demanded that you reduce the schedule by three weeks. What does this mean in terms of the Project schedule?

a. You have decided that fast tracking is the best option to pull in the schedule by three weeks

b. You have decided that crashing the schedule is the best option to pull in the schedule by three weeks

c. Your project has negative float

d. You cannot deliver the project three weeks earlier without impacting project quality

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/16
sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

Agreed with you,

......Thanks

Hafiz Sohail Ahmed
by Hafiz Sohail Ahmed , Procurement Assistant - Spare Parts , Emirates Flight Catering LLC

You cannot deliver the project three weeks earlier without impacting project quality

Deleted user
by Deleted user

Answers is 

c. Your project has negative float

Negative float of 3 weeks

Augustine Shayo
by Augustine Shayo , Student , UDOM

You have decided that fast tracking is the best option to pull in the schedule by three weeks

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – Notice the question doesn't ask you what you will do about it – it simply asks you ‘what does this

mean’? What it means is that your project now has a negative float of three weeks

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C