What is the primary difference between critical path (CPM) and critical chain (CCPM) schedule approaches?

 

a. There is fundamentally no difference

b. CPM focuses on managing float while CCPM focuses on managing buffers

c. CCPM focuses on extensive multi-tasking while CPM focuses on resource leveling

d. CPM uses heuristics while CCPM uses mathematical modeling

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/16
sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

B is teh answer,

Thanks for invitation

Utilisateur supprimé
par Utilisateur supprimé

b. CPM focuses on managing float while CCPM focuses on managing buffers

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – By definition, critical path method focuses on managing float while the critical chain project

management method focuses on managing buffers. Answer ‘A’ is incorrect, and answers ‘C’ and ‘D’ are red herrings