You have just completed your project activity, work package, and contingency reserve estimates. What have you created as a result of completing these estimates?

What have you created as a result of completing these estimates?

a. Bottom-up estimate

b. Cost budget

c. Cost baseline

d. Definitive estimate

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/17
Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

C. 

Cost baseline consists of estimated costs of activities/work packages and contingency reserves.

Utilisateur supprimé
par Utilisateur supprimé

Answer should be 

 

c. Cost baseline