Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You've set aside a certain amount of your project funds to cover key, identified risks. What specifically did you use to determine how much should go into this fund?

go into this fund?

a. Bottom-up estimate

b. Reserve analysis

c. Variance analysis

d. Upside-risk estimate

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/18
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

 

B – The reserve analysis is explicitly used for determining risk contingency reserve amounts.

 

 

 

 

Khatija Khatija
par Khatija Khatija , Senior Financial Accountant , Anglogold Ashanti

Budget Amount is determined by similar projects incurred. Increases in budget are determined by Inflation rate. Also research is done to determine "new costs" associated with the project. These costs are then included in the budget.

More Questions Like This