You are three months into a six month project. Assume the budget burn rate is constant. The budget at...

completion (BAC) is $,. AC = $,. The SPI =1.2. What is the CPI of this project? (Round to2

decimal places)

a.1.

b.1.

c.1.

d. It cannot be determined from the information given

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/18
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – This is a two-part calculation. You must first derive earned value from the SPI formula; SPI = EV/PV. At this point you know SPI (1.2) and PV ($60,000). Thus solving for EV you get: EV = 1.2 * $60,000 = $72,000. You can now compute CPI = EV/AC or $72,000/$65,000 = 1.11

Wasi Rahman Sheikh
par Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Agree with experts answer <<<<<<<<<<<<<<<<<,,

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

the answer is therer but the numbers in question is missed

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I think some numbers/figures are lost?