Several stakeholders on the project have been questioning the effectiveness of some of the technical team...

While the work is proceeding according to plan, some of the stakeholders are not satisfied with the work delivered to date, even though it meets requirements specifications. You have held several meetings with the stakeholders to try to get to the root cause of the problem. With some of the technical team present at these meetings, it becomes obvious that some of the stakeholders have had great difficulty in

describing what they want. As a result, some of the delivered product doesn't meet stakeholder expectations. Currently your CPI is1.3 and the SPI is .. What is your largest concern right now?

a. Clarifying the requirements collection process

b. The schedule

c. Managing stakeholder expectations

d. An increasing probability that some technical team members may leave the project due to high levels of frustration with stakeholders

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/18
Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

correct answer is C >>>>>>>>>