You are in the process of developing the quality management plan for your project. You have asked the technical team for some quality metrics...

that would be useful to document for the quality management plan. They've identified several other projects that are similar to this one, and seemed to think that the quality metrics established in these projects would also be applicable to the current project. This technique is called:

a. Quality audit

b. Process analysis

c. Benchmarking

d. Statistical sampling

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/22
Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Yes. Bench marking should be a process for developing the quality management plan

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

I think option C is appropriate.

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

Option C , bench marking,

Thanks for invite

Utilisateur supprimé
par Utilisateur supprimé

Benchmarking appears to be the most appropriate answer.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The correct answer - Option C , bench marking,