Your technical team has just identified a process that requires some corrective action. Corrective action is closest to:

a. Continuous process improvement

b. Defect analysis

c. Rework

d. Constraint analysis

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/25
Ruediger Dreissigacker
par Ruediger Dreissigacker , Project manager , ASCO Carbon Dioxide Ltd.

What are the defects?

What are the corrective actions?

How do the corrective actions effect on the production?

Do they have side effects?

Do other constraints occur after the corrective actions?

How can the new constraints can be eliminated?

If I'm not forced to choose only one option, I will choose all of them. If so, I will choose option (d), due to the fact that all other options are related to that.

Truong Thi Tuyet Hong
par Truong Thi Tuyet Hong , Planning Specialist , Terrain Services LTD. & Excel Consortium

Corrective action is closest to Rework

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

VINAY KUMAR GOSWAMI
par VINAY KUMAR GOSWAMI , Partner , 2MI

If it is Project Work - Answer will be REWORK

If it is business operations (BAU - Business As Usual) than it will be close to Continuous Process Improvement.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – Corrective action is closest to rework by definition. PMBOK® Guide, 5th edition, p. 559: “Action taken to bring a defective or nonconforming component into compliance…”

Piotr Teteruk
par Piotr Teteruk , IT Project Manager Roche , Roche

 

RCA  ( Root Cause analysis) is a structured facilitated team process to identify root causes of an event that resulted in an undesired outcome and develop corrective actions. The RCA process provides you with a way to identify breakdowns in processes and systems that contributed to the event and how to prevent future events. The purpose of an RCA is to find out what happened, why it happened, and determine what changes need to be made. It can be an early step in a PIP, helping to identify what needs to be changed to improve performance. Once you have identified what changes need to be made, the steps you will follow are those you would use in any type of PIP ( Performance Improvement Project) 

Ahmed Saeed
par Ahmed Saeed , Pyro operator , Glasnost

A.continuous process improvement which include process measurements and calculations Defect identification Defect reason analysis corrective action identification

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option B defect analysis, because corrective measures are usually identified in control quality process..

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

C is the best option.

Thanks...............

 

 