Which of the following is not true about error in project quality management?

 

A. It is an unavoidable component of all project work.

B. It is more costly than the design and planning work that would be necessary to prevent it.

C. It is a source of learning rather than a basis for disciplinary warnings or actions.

D. It is a reflection of inadequate project planning.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/04
Hrvoje Kancelak
par Hrvoje Kancelak , Certificated Traffic Engineer , Office of independent engineer

A. It is an unavoidable component of all project work.

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

option A is correct....................

Ramzi SAMRI
par Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

As I know I think A is the correct answer

Utilisateur supprimé
par Utilisateur supprimé

A is the coorect option because

According to the PMBOK, “The cost of preventing mistakes is always much less than the cost of correcting them” 

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

Option B

 It is more costly than the design and planning work that would be necessary to prevent it.

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

I think option a is applicable regarding the project.

Rizwan ahamed Haja moideen
par Rizwan ahamed Haja moideen , Technical Service Coordinator , Khalifa port Under sawaeed Employment LlC

It is a source of learning rather than a basis for disciplinary warnings or actions

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Option .......A. ..................

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Option D is the right answer. D. It is a reflection of inadequate project planning.