Register now or log in to join your professional community.
that the product will not have more than6 delivered defects. In a meeting with your team you decide that you will be following the CMMI framework and the project will be executed of Level4. You also decide that to control the defects you will be using control charts to monitor the defect density of each module. You in the middle of :
A. Plan Quality Process
B. Performing Quality Assurance
C. Performing Quality Control
D. Doing Quality Audit
Plan Quality Process is the most suitable answer
Thanks for invite,
Agree with you, the answer is A
Thanks for invitation , and the suitable answer is already unvield by Mr Muhammad Farooq
Your question is NOT CLEAR & COMPLETE.
Based on the key words used , I presume you are talking about Project Quality Management. If that is the case , Project Quality Management is all about planning and following the processes and activities ( by performing organization, usually ) to meet the Project Requirements with Zero or Minimum variations keeping Stakeholder Satisfaction in mind all the time.
In performing quality control
Performing Quality control is the right answer because Control charts are used to control the defects and stage is at Quality control
thanks for invition ,,,,,,,,,, my choice is option C
Option C is the correct answer. control charts comes under monitoring and control process