Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are managing a very large project that is very critical to your client. You have promised the client?

   that the product will not have more than6 delivered defects. In a meeting with your team you decide that you will be following the CMMI framework and the project will be executed of Level4. You also decide that to control the defects you will be using control charts to monitor the defect density of each module. You in the middle of :

A.  Plan Quality Process

B.  Performing Quality Assurance

C.  Performing Quality Control

D.  Doing Quality Audit

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/09
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

  Plan Quality Process is the most suitable answer

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

Thanks for invite,

Agree with you, the answer is A

Utilisateur supprimé
par Utilisateur supprimé

Thanks for invitation , and the suitable answer is already unvield by Mr  Muhammad Farooq 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Your question is NOT CLEAR & COMPLETE.

Based on the key words used , I presume you are talking about Project Quality Management. If that is the case , Project Quality Management is all about planning and following the processes and activities ( by performing organization, usually ) to meet the Project Requirements with Zero or Minimum variations keeping Stakeholder Satisfaction in mind all the time.  

Hrvoje Kancelak
par Hrvoje Kancelak , Certificated Traffic Engineer , Office of independent engineer

In performing quality control

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Performing Quality control is the right answer because Control charts are used to control the defects and stage is at Quality control

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option C is the correct answer. control charts comes under monitoring and control process 

More Questions Like This