You are the project manager working on constructing a suspension bridge for the city of San Francisco. You've just conducted an earned value, what do you do in the following scenario?

 

analysis and determined that the CPI index is1. and SPI index is1.. Specifically, your project is coming in ahead of schedule and under budget. However, one of your structural engineers informs that he is afraid that the welding does NOT meet quality standards. Unfortunately, sub-par quality in the welds could reduce the stability

of the bridge, especially is the earthquake happens. Hence, you are working with the

quality assurance department to verify that whether the project will satisfy the necessary quality standards. All of the following are required in order to start this process EXCEPT:

A. Work performance information

B. Quality control measurements

C. Quality metrics

D. Recommended corrective actions

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/06/11
Ghada Eweda
by Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

Agree with experts answers . thank you

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My oppinion is that the right answer is:

D. Recommended corrective actions

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

To verify the project against quality standards, I don't think corrective actions are required, hence option D should be the right answer

Deleted user
by Deleted user

Correct answer is 

D. Recommended corrective actions

Wasi Rahman Sheikh
by Wasi Rahman Sheikh , Warehouse Supervisor , AL MUTLAQ FURNITURE MFG

Thank you for inviting for answer _--- I will be wait for more experts answer

Deleted user
by Deleted user

Option A  seems  closest  answer.

My name is Ashley Vivian, Am here to share a testimony on how Dr Raypower helped me. After a 1/5 year relationship with my boyfriend, he changed suddenly and stopped contacting me regularly, he would come up with excuses of not seeing me all the time. He stopped answering my calls and my sms and he stopped seeing me regularly. I then started catching him with different girls several times but every time he would say that he loved me and that he needed some time to think about our relationship. But I couldn't stop thinking about him so I decided to go online and I saw so many good talks about this spell caster called Dr Raypower and I contacted him and explained my problems to him. He cast a love spell for me which I use and after 24 hours,my boyfriend came back to me and started contacting me regularly and we moved in together after a few months and he was more open to me than before and he started spending more time with me than his friends. We eventually got married and we have been married happily for 3 years with a son. Ever since Dr Raypower helped me, my partner is very stable, faithful and closer to me than before. You can also contact this spell caster and get your relationship fixed Email: urgentspellcast@gmail.com or see more reviews about him on his website: https://urgentspellcast.wordpress.com WhatsApp: +1 (209) 783-8804

Adeel Ibrar
by Adeel Ibrar , Projects Planning Manager , KPS Limited

The answer is C quality matrix

harish kumar
by harish kumar , Customer Service Officer , icici bank

Financial risk management is the practice of economic value in a firm by using financial instruments to manage exposure to risk: operational risk, credit risk and market risk, foreign exchange risk, shape risk, volatility risk, liquidity risk, inflation risk, business risk, legal risk, reputational risk, sector risk ‎

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

I think D is a suitable answer..