You are involved in monitoring specific project results to determine whether they comply with relevant quality standards. You are using?

a control chart to illustrate how a process is behaving over time. You've constructed your control chart and determined that all the data points are within the upper and lower control limits of the chart. In addition, seven consecutive data points are observed to be on the one side of the mean. Which of the following is your BEST plan of action?

A. Compare the results from the lat quality management plan

B. No additional action is needed, as the process is within control

C. Adjust the mean based on the observed data points

D. Identify the assignable causes

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/14
Utilisateur supprimé
par Utilisateur supprimé

suitable answer is 

D. Identify the assignable causes

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

option D is best choice.............

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

D. Identify the assignable causes...............

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

yes of coarse , standard quality measures are indication of correct approach to the specfic quality measures it is advisable to be close to them as much as possible , for example if wws scrab rate is defined to be 1% then there is obligation to abide by that standard

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I thing that the right answer is D

Muhammad Ahmed
par Muhammad Ahmed , Quality Assurance Executive (South Region) , K&Ns Foods Pvt.Ltd.

D. Identify the assignable causes

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

D Option,

Thanks for invitation

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Yes Option D is the apt answer because 7 concecutive data points from mean means assignable cause should be identified to correct it

kamal purbia
par kamal purbia , IT Project Manager , Automated Systems Company

D. Identify the assignable causes

 

seven consecutive plot point are above or below the mean suggest that process is out of control, therefore identify the assignable causes.

 

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D