Implemented change request, implemented corrective actions and implemented preventive actions are inputs to which process?

 

A. Quality planning

B. Perform quality control

C. None of the choices are correct

D. Perform quality assurance

E. Direct and manage project execution

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/06/17
Utilisateur supprimé
par Utilisateur supprimé

Correct answer is 

D. Perform quality assurance

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

D. Perform quality assurance

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:D. Perform quality assurance

Sathish Prabhu.V
par Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Even though both B and D are close to correct answers, I would prefer Option D Quality Assurance, since Implementing Change request, Corrective Action and Preventive action are action for Quality Audit

Ramzi SAMRI
par Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

I agree with Mr Tarek, d is the suitable answer.

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

I think option D is the correct answer

Usman Islam
par Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option C. In my opinion ......

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

Gayasuddin Mohammed
par Gayasuddin Mohammed , Advocate , Practicing Law before High Court at Hyderabad

I think the best option (E) as a Agile process. thanks.

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

in quality it is related to quality assurance as previously answered , in maintenance it is related to preventive and corrective  maintenance