Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
During the project, however, the vendor refuses to accept this commitment as it was not included in the subsequent Contract. The Vendor:
A. Is incorrect, as vendor is obliged to everything that was agreed
B. Is correct as they are bound by the contract only
C. Is insensitive and should accept this in view of long term relationship
D. Should accept if the cost involved is small
The most suitable answer is Option B. Is correct as they are bound by the contract only
if a document is signed then it is a commitment , asigned contract is an obligation to all parties
My opinion is that the right answer is:
B. Is correct as they are bound by the contract only
Agree with MR Muhammad Farooq
Contract is the only authentic document between the parties.
Correct answer is B.
Thanks for invitation
A. Is incorrect, as vendor is obliged to everything that was agreed
B is the answer,....
Thanks
Answer is B.
Any commitment not in the contract does not have to be met even though it was agreed upon during negotiations because contract supersedes all negotiations, discussions, memos, agreements etc. before signing the contract.
C. Is insensitive and should accept this in view of long term relationship