A document which describes how the project management team will implement the performing organization’s quality policy, what is it?

 

a-Qualityassuranceplan

b-Qualitymanagementplan

c-Qualitycommitment

d-Qualityaudit

user-image
Question ajoutée par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date de publication: 2016/07/19
TARIG BABIKER AL AMIN
par TARIG BABIKER AL AMIN , Head of Planning and Studies Unit , Sudanese Free Zones and Markets Co.

Thanks for invite ... B is the document : Quality Management Plan

حفصة المستظرف
par حفصة المستظرف , سكرتيرة , مكتب محاماة : المحامية :خذيجة فاروق

Thanks Mr Mohammed for invitation :

b- Quality management plan

Yaqoub Alomar
par Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality

b-Quality management plan

I agree with my colleagues

Nadjib RABAHI
par Nadjib RABAHI , Freelancer , My own account

I agree with the majority of answers

b : Quality management plan

Omar Saad Ibrahem Alhamadani
par Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

It is Quality Management Plan ....

Anmol Srivastava
par Anmol Srivastava , Project Engineer , Dar al Handasah

Quality Management Plan

It lays down standards and procedures that are developed inorder to attain Project quality objectives and allign Company quality policy to Project Quality plan. An important principal behind developing this plan is ensuring its suitability towards resource capabilities and existing order associated to concerned project.

Quality Assurance plan lays down a checklist and process specific instructions.

Quality commitment is an assuring statement, confirming allignment of Project Quality policy to Companies Quality Policy.

Quality Audit is also a checklist (brief notations) that may be internal or third party linked. QA forms backup reference for establishing Learning curve and quality achievements & certification.

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-b Quality management plan

Ahilan R
par Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

Answer is     b : Quality management plan

mohammed negm
par mohammed negm , مدير مبيعات , مؤسسة أطياف لتجارة المواد الغذائية

Thanks for the invitation, it  is quality mangement plan

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

I would like to choose option B as my answer.

Utilisateur supprimé
par Utilisateur supprimé

Thanks for invitation -

With the choice - B .