A. Reducing costs to the buyer.
B. Controlling contractor costs.
C. Aligning contractor and buyer goals.
D. Reducing production costs.
E. Reducing contractor risk.
The right answer is: C
Option C is the correct answer according to my knowledge and all the other options don't fit in here.
Answer is C. Aligning contractor and buyer goals.
The purpose of the incentive is to provide a motivation to be more efficient and effective. Cautioned to say if the contract is not designed as an instrument to effect this and the parties are not collaborating with shared outcomes and goals, it will get lost in translation. Simply put if you want to incentivise a contract then you need the following in your agreement:
Trust me when i say not many people get this right. The defaul is usually conflict and confusion in an adversarial context.
Reducing costs to the buyer.
I think negotiation of cost & Terms between buyer and supplier is that.
i think answer c is the right one
C. Aligning contractor and buyer goals. Correct Answer.