Which is not an example of a correctly handled Contract closure procedure?

 

 

A. Early termination of a contract because of arepudiatory breach

B. Settling and finally closing the contract agreement

C. Early termination of a contract because of an immaterial breach

D. Product verification by stakeholders and administrative closure

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/07/30
Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

C. Early termination of a contract because of an immaterial breach