According to the PMI, early termination of a contract is considered a special case of?

A. Contract severance

B. Contract default

C. Contract cancellation

D. Contractual severance

E. Contractual non-performance

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/08/07
appa anand badipetla
par appa anand badipetla , Deputy Manager-Designs , PES ENGINEERS PVT Ltd

Contract cancellation.Earlier termination can happen when both parties agrees to terminate project on mutual aggrement.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The best option is

A. Contract severance

Marvin Malquisto
par Marvin Malquisto , DEPUTY CONTRACT MANAGER (short contract only) , Samsung C&T

procurement closure that result to mutual agreement of both parties.