If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be ?

A. started5 days later B. completed5 days later C. performed at slower rate in days D. all the above

user-image
Question ajoutée par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date de publication: 2016/08/09
safi eljim bousaada
par safi eljim bousaada , Senior project manager, certified PMP, PSM-I, PSPO-I , Saphir Consult

D. all of those.

The free float allow to delay the end date of the activity without delaying the early start date of its successor.

Abdelrahman Owais
par Abdelrahman Owais , Sr. Mechanical Engineer UPDA Certified , Electrowatt

The correct answer is:

D. All the above

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

it can be critical path if iam not mistaken

Rohanjit Menon PMP
par Rohanjit Menon PMP , Senior Manager Business Development , Zuti Engineering Solutions

It is B. Completed 5 days later.

It can be A. as well. But if the activity has different rates of completion, you should be most concened with its late finish time. Hence, B.

Syed Muhammad Raza Abidi
par Syed Muhammad Raza Abidi , Senior Automation and Controls Engineer , Rivian Inc

according to my knowledge, float is ES - LS so we can have 5 days delay or slower. so it should be C

MD RASHID RAZA
par MD RASHID RAZA , qa/qc civil engineer , Arkitechno consultant india limited

Completed in 15 days later.