Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. started5 days later B. completed5 days later C. performed at slower rate in days D. all the above
D. all of those.
The free float allow to delay the end date of the activity without delaying the early start date of its successor.
The correct answer is:
D. All the above
it can be critical path if iam not mistaken
It is B. Completed 5 days later.
It can be A. as well. But if the activity has different rates of completion, you should be most concened with its late finish time. Hence, B.
according to my knowledge, float is ES - LS so we can have 5 days delay or slower. so it should be C
Completed in 15 days later.