Your project is coming to an end, and you are in the process of listing the activities that must be performed to close out the project See below?

Which of the following should be performed during the closing processes?

A. Request final inspection reports for all vendor supplied products

B. Issue payment schedules and requests

C. Issue a formal notice of project completion to sellers

D. Seek legal counsel from the company's attorney prior to closing the project

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/08/14
Antonio Baga
par Antonio Baga , Agreement Specialist / Administrator , Qatar Petroleum

 Issue a formal notice of project completion to sellers

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The appropriate option is

C. Issue a formal notice of project completion to sellers

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option -A Request final inspection reports for all vendor supplied products