Which of the following statements are true?

A. Procurement audits review the procurement process from plan contracting to contract closure

B. Procurement audits review the procurement process from plan purchases and acquisition to contract closure

C. Procurement audits review the procurement process from plan purchases and acquisition to contract administration

D. Procurement audits review the procurement process from plan purchases and acquisition to close project