Your company develops large commercial and industry real estate. In you current project, you have been asked to manage the ? See below for detail

construction of a-story office building. Which document describes the business needs for this project, identifies key deliverables, and gives you authority to begin the project and start assigning resources?

A. Work authorization form

B. Ishikawa document

C. Executive summary

D. Work break down structure

E. Project charter

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/08/20
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most appropriate option is

E. Project charter

Gayasuddin Mohammed
par Gayasuddin Mohammed , Advocate , Practicing Law before High Court at Hyderabad

D. Work break down structure