You are in process of exterminating which set of project activities will take the longest to complete? See below for detail

Which of the following is the MOST appropriate tool to use?

A. RBS

B. Gantt chart

C. WBS

D. Milestone chart

E. Network diagram

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/08/20
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most appropriate option is

E. Network diagram

Utilisateur supprimé
par Utilisateur supprimé

A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time. 