A. Risk register
B. Project scope statement
C. Project cost management plan
D. Risk management plan
E. Performance reports
F. Project schedule management plan
Answer: E
Option # E........but i saw wrongly you have shown the correct answer.
E. Performance reports.
You have answered the question by yourself, If I am not wrong.
Thanks for the invitation.
Answer is E - Performance reports.
Next step after identifying risks is to do Qualitative & Quantitave analysis of the identified risks for which performance reports are not required.
the least helpful input is Project scope statement