Which of the following BEST describes the “point of total assumption” for a contract?

 

 

 

A. The point in a cost-plus contract where the buyer assumes that the seller will need to be paid

B. The total cost of a T&M contract

C. The point in a fixed price contract where the seller has to assume all costs going forward 

D. The total number of resources required for a contract

 

 

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/02
Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C. The point in a fixed price contract where the seller has to assume all costs going forward.

Since Fixed Price contract has the highest risks considering all assumptions (Scope of works)

Ghulam Farid
par Ghulam Farid , Contracts Officer , Abu Dhabi Company for Onshore Petroleum Operations (ADCO)

Yes I endorse Mr. Ahmad's response as PTA is falling under FP/ Insentive contracts

Utilisateur supprimé
par Utilisateur supprimé

Don't have time go into details:

https://en.m.wikipedia.org/wiki/Point_of_total_assumption

 