If claim for extension of time is approved by Engineers/Project Management/Client, what should project manager take next step for his company?

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/09/05
mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

a change of time or extension of the time of the project means simply that the whole plan will be hindered including the critical bath or time plan or productivity schedules or human or equipments used efficiency that the project manager should take things lighted he should review every things that contributed to the extension of time , before he approve it he should justify clearly why is extension is needed and how does that reflect on the cost and expenses and he should take the matter serious and give prompt time for complete execution of the project and report all to the senior management and claim their approval as well   

Mohammed Esaam Qasam
by Mohammed Esaam Qasam , مشرف مبيعات عام , شركة الخمائل العالمية

Thank you for the invitation . I agree with the engineer Walid Alnuaimy 

Deleted user
by Deleted user

Thanks for invitation -

       Here he must go back to the contract for therequired details and then take the appropriate  *decision

Abdul Hakkim Chirakkandam
by Abdul Hakkim Chirakkandam , Project Head (own company) , M/S. C A Abdul Hakkim

He should go throgh the terms and condition mentioned in the contract document, regarding extension of time of completion. Accordingly he can only approve the time of extension.

Mohammed Asim Nehal
by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

Thanks for invitation,

Make a change request and revalidate the project schedule, revise the project plan with time, cost , delivery etc. Inform one and all.

Deleted user
by Deleted user

Thanks for the invitation! I agree with Mr.Moukthar would apply necessary changes to project plan accordingly.

Elke Woofter
by Elke Woofter , Project Assistant , American Technical Associates

extention of time also means higher cost ...

Who is paying for this?

Is there enough funding there to pay personnel and equipment rental?

What is the new timetable and delivery/completion date?

What is the additonal cost? 

 

Tamer Safei Eldin
by Tamer Safei Eldin , Managing Director, Board Member , El Obour for Real Estate Investment

The PM will report the effect of prolongation on the project cash-flow & get his mitigated schedules, resources & invoices milestone accordingly.

Mohamed Youssef
by Mohamed Youssef , Managing Director And Founder , MY Development

I assume from your question that you mean the Contractor's Project Manager. In such case and according to FIDIC, after the approval of extension of time by the Employer (client), then the Contractor should update/modify the work plans within7 days. Also, in case there is an additional cost involved as a result of the extension of time (at no fault of the Contractor), then a notice and a claim should be submitted to the Engineer/PM/Employer for the additional cost. Please note that other types of contracts may have different conditions, so it is important to specify the type of contract and apply its conditions.

Deleted user
by Deleted user

Thanks for good invitation ,

Solve the problems that caused delays, quickly + agree with experts opinions

 

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

Any extension of project time means a delay for the whole project, consequently project cost.

 

PM should review terms and conditions to check for penalties because of that delay, then maybe he/she should review all remaining project milestones to see if execution time can be shrunk to avoid any penalties due to project delay.