Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
a. Back-charge contracts
b. Fixed-price contracts
c. Progress payment contracts
d. Cost-plus contracts
D cost plus Contract since adding the mark up on the cost incurred
A not correct back charge contract which means client/ contractor incur cost due to failure to execute by sub-contractor or main contractors
B not correct fixed price contract mean lump sum contract
C not correct progressive payment contract is method of payment and not a contract
D. Cost-plus contracts ----------
d. Cost-plus contracts..........................................
My answer is option (D) -----------
My answer is option D) Cost-plus contracts
Thanks for your invitation, My reply is Option D.
Thanks for the invite.
My answer is D-Cost Plus Contracts.
Answer is:d. Cost-plus contracts
d. Cost-plus contracts is my option