A project manager wants to subcontract part of the project. This part of the project is quite complicated, and there are many ways that the work:

can be done. What method of request for seller responses should be used by the project team?

A. Request for bid

B. Request for quotation

C. Request for proposal

D. Request for information

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/17
Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

C. Request for proposal................

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

My answer to this question is option C

Terrence Walmsley
par Terrence Walmsley , Owner , The Awesome Group of Companies

C.

Given that you have complexity surrounding the process requirements, you would want to feel confident that the third party was capable....

Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Option-C: Request for proposal

When a part of the project is quite complicated, it needs innovative ideas from the suppliers. So, in this case the answer is  “Request for Proposal”

Ghulam Farid
par Ghulam Farid , Contracts Officer , Abu Dhabi Company for Onshore Petroleum Operations (ADCO)

C, RFP will deal with complicated work

Utilisateur supprimé
par Utilisateur supprimé

Thanks for the invitation,in regards to the question usually thats really happens in the pratical life however best way to request for the proposal.

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your invitation. Option C, Request for the proposal.

Utilisateur supprimé
par Utilisateur supprimé

The answer is option C on this question

Ihab Zaki
par Ihab Zaki , Chief Technology Officer (Cto) , EGID

Option C, request for proposal