What are performance reviews held to?

A. Correct the project manager's mistakes.B. Provide for answers for upper levels of managementC. To assess project status or progressD. To apprise the project costs and cost trends of the project

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/24
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite. 

It is C - To assess project status or progress. 

Option (C). To assess project status or progress

AhmadReza Mardani
par AhmadReza Mardani , Engineering Project Manager , Danone Dairy Pars

 Performance reviews are held to to assess project status or progress.

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Sure Option-C.......................................................................................