Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are on the project selection team and must decide on only one project to approve. Of the following 2 possible project which would you select?

why?Calgary: payback period is months ,and NPV isToronto: payback period is months, and NPV isA. project Toronto because because the NPV is the highest number.B. project Calgary because the payback period is shorter than the project Toronto.C. Can not be determined based on the information provided.D. project Calgary because the NPV is positive and the payback period is sooner than Toronto.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/25
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Scenario is selection of mutually exclusive projects. In that case I would go for the project with higher NPV. Since options provided are not clear to me, my answer shall be C - Can not be determined based on the information provided.

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C,  Can not be determined based on the information provided..............................

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Option C is appropriate answer.

More Questions Like This