You have negotiated a major deliverable with a contractor several of your colleagues have utilized in the past without problems?

Its is critical the contactor meet an Augustth deliverable.this is an example of (n):A. ObjectiveB. GoalC. Constraint.D. Assumption.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/09/25
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion D. Assumption -------------------------

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Most appropriate among the given options is B - Goal .

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

C. Constraint...............

Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

The choice is C.

The contractor perform according to WBS objective and so the choice is C.

Goal, constraints and assumptions are handled and controlled by the project management itself

Option (A) Objective -------------------------

Imran Ahmed
par Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-A, Objective.......................................................