Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What are the steps you should take formally to stop the project?

A. generating ,gathering and disseminating information to formalize the phase or project complition.

B. collecting and disseminating performance information.

C. completing and settling conracts, including resolution of any open items.

D. both A and C

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2016/09/30
Nadjib RABAHI
par Nadjib RABAHI , Freelancer , My own account

The answer is : Option D- both A and C

Utilisateur supprimé
par Utilisateur supprimé

The steps :

1- Knowing the reasons  .... (+ yes or - no )

2 - Study contracts ..... (+ yes or - no )

3- Comparison of actual and theoretical costs .... (+ yes or - no )

4- Follow-up workers and working ..... (+ yes or - no )

5- Review project materials ..... (+ yes or - no )

6- Review schedules ..... (+ yes or - no )

7- Audit of the financial and moral benefits ...... (+ yes or - no )

Finally : it was +++ yes >>> --- no ... in this case must stop ,

Before that , my answer ( D )

..... Thanks .

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

These primary areas of the shutdown process are: • Personnel • Operational Capability/Requirement • Technology • Facilities/Hardware/Software/Program Security • Contracts • Budget

Utilisateur supprimé
par Utilisateur supprimé

option (D) is the correct answer

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

It is option C.

First thing to do before stopping a project is " completing & settling contracts including resolution of any open issues / items ". 

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?