Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Your project you just complited , was the first time your company ever contracted a third party vendor to perform some of the project work.

    

As part of the close out process,you are documenting the lesson learned. Which of the following is the contract lessons learned include?

A. A complete list of the contract as built drawing.

B. Feedback customer.

C. The procurement process since this was the first time the company negotiated a contract.

D. Evaluations of what went right and what we could have done better.

 

 

 

 

 

 

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/10/08
Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. I would like to choose option D as my answer.

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

D. Evaluations of what went right and what we could have done better.

Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Option D:  As .l.Lesson learned is evaluations of

  1. what went right,
  2. what went wrong and
  3. what we could have done better.

 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Option A - A complete list of the contract as built drawing is the most appropriate answer. 

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

I seem A is comparatively good answer. 

Utilisateur supprimé
par Utilisateur supprimé

option (D) is the correct answer

 

More Questions Like This