Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
What technique will u use to determine the confidence level and the probability of completing the project on a specific day ?
A. PERT formula.
B. Monte carlo simulation.
C. Probability analysis.
D. Varience analysis
My answer is option (C) -----------
Thanks for the invite.
It is B - Monte Carlo simulation.
Monte Carlo simulation gives more accurate time estimate.
option c probability analysis
I seem Option C is good answer