Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Several of the functional managers have very different views on how the project should be managed and what the deliverable should be.As the project manager for this project for this project which of the following is the best thing for you to do?
A. Ask the client when they will be in agreement on project requirements.
B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.
C. Make sure the terms and conditions of the contract are very very clear especially how changes will be managed.
D. Advice the client they must reach agreement on both issues within2 weeks, Otherwise, the schedule have to be defferred until they are able to agree as a
Answer:
Option B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.
My answer is option (B) -----------
decisions and alternations are always taken by total understanding and coordination with the concerned managers and engineers , i think the answer is B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.
Thanks for your invitation. Option B is a convenient answer in this case/ four choices.
My is also as like as above experts option -B.
Thanks for the invite.
I will go with option B as it appears most appropriate of all.
My oppinios is that the right answer is B.