Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

All program managers have been asked to come up with a new estimate at completion for their in-progress project. What is the most accurate method to develop?

the new estimate is to:

A. Complete an earned value analysis to determine the cost analysis.

B. take the actual to date and add the remaining budgets modified by performance factor.

C. take the actual to date and develop a new estimate for all remaining work.

D. Add the remaining budget to what has already been spent.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/10/09
Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

C. take the actual to date and develop a new estimate for all remaining work.

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your invitation. Option C which is fit with most accurate method to develop.

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

I am also agree with honorable Bangladeshi brother Mr Md Fazlur Rahman. Option C.Take The actual to date & develop a new estimate for all remaining work.

Ksenija Kancelak
par Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I think the right answer is C

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

I go with option C - take the actual till date and develop new estimate for remaining work .

More Questions Like This