The cost baseline is developed during which process?

A. Perform integrated change controlB. Estimate costsC. Develop scheduleD. Determine budget

user-image
Question ajoutée par DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date de publication: 2016/10/12
Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is option D

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In process Determine project Budget   -    Option D

Bass Fakih
par Bass Fakih , IT-BackOffice , New York Presbyterian Hospital

The cost baseline or project budget is developed in the Determine Budget process which is a planning process in project cost management therefore D is the answer

ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The cost baseline is developed during budget. My answer is D