Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is known about the Contractor's Daily Report and what does it contain?

user-image
Question ajoutée par أحمد حمدي الزواوى , Project Manager,Projects Manager , M.A.ALSOBHI COMPANY
Date de publication: 2016/11/22
mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

daily contractor report in include execution of t project % , production per that specific day , outstanding problems and their solution if any , supply issues, obstacles that delay the project , materials issued per balance per demand per lead time , activists carried out in brief , cost / pity cash issued , cost , payments required with execution percentage

Tamer ElGhazouli
par Tamer ElGhazouli , Technical Office Manager "Deputy Project Manager" , GAMA Construction

simply its a site summary sheet that include but not limited to the following:

1-total number of site teams ( managers,engineers,staff,supervisors,labors,safety,security ...etc.)

2-list of on going activities in all disciplines ( earth work, civil,  MEP ,finishes ) and some times progress %

3- list of equipment , subcontractors

 

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I agree with Mr. mamoun mokhtar

Utilisateur supprimé
par Utilisateur supprimé

Daily site report should provide status updates on site progress and daily safety on fixed formats provided by project manager in collaboration with planning and safety department. Fixed formats is useful in containing the content required and officially communicated for reasons of baseline plan, cost tracking, audits requirements and parameters which can be compared across similar projects for greater efficiency in resource allocation and action plans on schedule variance if any

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Contractor's Daily report is a document that should tell what he has done on a particular day. Daily report which is normally generated from the site is a written communication between a contractor and project management office about the progress of the work at site or the issue/s that are tackled on the specific date of the report.

Ashraf E. Mahmoud (PhD)
par Ashraf E. Mahmoud (PhD) , University Lecturer, Freelancer Consultant and Trainer for Int'l Business & Banking TF. , FreeLancer

Thanks for invitation,

I do support all the colleagues' specialized answers.

nada arab
par nada arab , General Manager

* PRESENCE OF LABORS AT SITE .

* REPORT OF WORK PROGRESS 

*PROBLEMS FACING AT SITE .

*MATERIAL NEED FOR WORK 

* WORK ACHIEVED DURING THE DAY 

*SOLUTION FOR PROBLEMS THAT MAY FACE AT SITE . 

*WORKING HOURS FOR EACH WORKER 

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

I agree with colleagues answer

 

And add necessary to provide scheduling control report and the report of the project to ensure quality

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. I agree with the given answers.

Utilisateur supprimé
par Utilisateur supprimé

Thanks for invitation -

 

All technical information relating to the functions of his work as a contractor       !!!

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think Mamoun reply cover almost all aspect of daily report so agreed with his reply