Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Analogues estimating is most accurate when:

 

A. previous projects are similar in fact not just appearance.

B. there is a relationship between the cost being estimated and known parameter.

C. the historical information used to develop the model is accurate.

D. work items are very small

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/11/26
hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

Option A

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most appropriate answer is option A

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your question. Option C - the historical information used to develop the model is accurate. 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation and my first choice is option A . If option A was not there I would have gone with option C .

mamoun mokhtar
par mamoun mokhtar , general manager , albyan technical foungary

historical reference is used when the history occurred recently, my answer is C. the historical information used to develop the model is accurate.