In cost monitoring, the s-curve depicts the relation between:

 

A. Schedule complition and time.

B. Cumulatives value and time.

C. Schedule complition and value resources.

D. resources and time

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/11/26
Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option B - Cumulative value and time.

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is option B - Cumulative value & time and thanks for the invitation.

 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Option B is most suitable answer ---------------------