Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The inputs of the Performance Reporting process include all of the following except for which one?

 

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/12/17
Deleted user
by Deleted user

C. Forecasted completion... thats what does not come under Performance Reporting process

Mohamed Shaker Eissa
by Mohamed Shaker Eissa , Training & SFE Manager , Abbott Nutrition

Question number 2 ( Work Performance Informantion )

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable answer is  A. Performance reviews

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option C- Forecast Completion. Many thanks for your invitation.

Ahmed Hejazi
by Ahmed Hejazi , Projects Manager , Jadat Itqan Consulting - JIC

Forecasted completion is not an input to performance reporting process 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

I will go with option C .

More Questions Like This