Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you don't correct this.
A. The project costs could increase, there might be rework, and schedule delays might result.
B. The project management plan's process for verification and acceptance of the deliverables needs to be updated as a result of the poor scope definition.
C. The poor scope definition will adversely affect the creation of the work breakdown structure, and costs will increase.
D. The stakeholders will require overtime from the project team to keep the project on schedule
It is Option A. Thank you for your invitation.
The most appropriate option is #A
Options: B, C, and D are could happen if the poor scope of work was not corrected
In my opinion, options A , B , C will happen .
Thanks for the invitation. My answer is C
Thank you for the invitation
Option #A
My answer is for option (A)
Thank you for invitation. I seem option A is appropriate.
All the listed effects will happen if the scope definition is not rectified