Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. Takes the longest time to complete
B. Allows some flexibility in scheduling a start time.
C. Is not affected by schedule slippage
D. Must be done before any other tasks
E. All of the other alternatives apply.
My answer is for option (A) Takes the longest time to complete
Thank you for invitation. I seem option A is appropriate.
Is the path that connects the critical activities which starts from the beginning of the project and ends at the end of the project, which is the longest path in terms of the length of time in the networking scheme. On this path there is no time margin for maneuver in the implementation of any task due to lack of time in excess of any task on this track.
Thank you for the invitation
Option A
Takes the longest time to complete is the correct answer - Option A.
Of course it is A - takes longest time to complete & thanks for the invite.
A. Takes the longest time to complete
A critical path need not be only the longest path. It constitutes all the critical activities where the total float = zero.