Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The critical path in a schedule network is the path that:

 

A. Takes the longest time to complete

B. Allows some flexibility in scheduling a start time.

C. Is not affected by schedule slippage

D. Must be done before any other tasks

E. All of the other alternatives apply.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/12/23

My answer is for option (A)  Takes the longest time to complete

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option A is appropriate.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Is the path that connects the critical activities which starts from the beginning of the project and ends at the end of the project, which is the longest path in terms of the length of time in the networking scheme. On this path there is no time margin for maneuver in the implementation of any task due to lack of time in excess of any task on this track.

Thank you for the invitation

Option A

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Takes the longest time to complete is the correct answer - Option A.

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is A - takes longest time to complete & thanks for the invite.

RAJASEKHAR NAGULA
par RAJASEKHAR NAGULA , Associate Director , AECOM

A. Takes the longest time to complete

Binil Paul
par Binil Paul , Sr. Planning Engineer , KEO International Consultants

A critical path need not be only the longest path. It constitutes all the critical activities where the total float = zero.

More Questions Like This