A. Estimate Costs
B. Estimating Activity Duration
C. Control Costs
D. Determine Budget
Thank you for invitation. I seem option - C. Control Costs is good answer.
I beg to differ with you Mr.Muhammad , Reserve Analysis technique is used in Control Cost as well.
In control cost process Reserve Analysis is used to monitor the status of reserves ; to determine whether the same reserves will do or additional reserves needed .
Thanks for the invitation.
I think option C because
Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as
costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control
Costs.
Thank you for the invitation. My answer is B
My answer is for the option (B)