You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following?

 

A. Using the previous project's alternatives identification as a template

B. Reusing the previous project's product description when writing the scope statement

C. Using the previous project's WBS as a template

D. Reusing the previous project's cost-benefit analysis as justification for this project

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/13
sodiq lawal
par sodiq lawal , Quality Inspector , JEFFERSON CONTRACTING CO.

the work break down structure of the former project is of course needed as a template and variations are accounted for. After which the cost of undergoing the project at the present time is justified against the benefit of the former similar project. 

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for your invitation. It is Option C. Using the previous project's WBS as a template.

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Most appropriate choice, in my opinion is C - as a WBS template & thanks for the invite.

Ronak Agarwal
par Ronak Agarwal , Finance Manager , MUST WORLD DMCC

Using the previous project's WBS as a template

Mohammad  Anwar Rizwi
par Mohammad Anwar Rizwi , Project Control Manager , Icon Construction LLC

As a cost engineer, I will take the benefits of WBS and Cost benefits from the previous experience. although all the options are useable but Cost of the project is my prime concern. 

Jagadeesh Challa
par Jagadeesh Challa , Project & Application Manager , Doha Cables

I do choose the Option C & D.

As you know, for any Project the main aspects are Cost, Scope and Time. To reduce the Cost and Time, I can reuse my Previous Project's  WBS as a Template and Cost Benefit Analysis to fulfill my current Project needs as it will give me a Justification for reusing in future prospective.

Utilisateur supprimé
par Utilisateur supprimé

Thanks for the invitation and i agree with Mr.Challa.

Mishal Basheer
par Mishal Basheer , Senior Project Engineer , Qatarian Western Equipment Trading Company W.L.L (QWETCO)

Option C is most appropriate.

All others are variable at dependent on project and its deliverable, hence it changes with project scope, and client requirement. 