In crashing a task, what would you would focus on?

 

A. Accelerate performance by minimizing cost.

B. As many tasks as possible and accelerate performance by minimizing cost.

C. Non critical tasks.

D. Accelerating performance of tasks on critical path.

E. As many tasks as possible.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/21
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given , option D appears to be most appropriate.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

Option D