A. Both1) the severity of the consequences, and2)how likely the event is to occur with risk.
B. (Cost + Benefit + Business Risk) / Insurable Risk.
C. how likely the event is to occur with risk.
D. Risk Probability x Amount At Stake.
E. the severity of the consequences.
D. Risk Probability x Amount At Stake
Term " Risk Event Status " is not a valid term as per PMI ; thus, in my opinion, given options mean nothing.
Although PMI is not using term "Risk Event Status", but this term is used alternatively for "Risk Rating".
Both the terms point to the same concept of measuring the level of the risk using its probability & impact.
I believe A & D are the same answers but I'll choose A.
To get more information on Project Management, follow the following page:
In my opinion, The appropriate option Is D. Risk Probability x Amount At Stake.
the answer is A
it's usually presented in a Matrix, that shows the probability in a column and severity in a bottom row. The risk event status is the result of multiplying the probability by the severity.